Temporary Traffic Orders for energy pipe works

Here is the wording of the TTRO:

OXFORDSHIRE COUNTY COUNCIL

ROAD TRAFFIC REGULATION ACT 1984

Section 14(1) & (7)

Notice of Temporary Traffic Order Oxford, Various Roads Headington Temporary Traffic Prohibitions

Date of Order: 29 December 2015 Comes into force: 4 January 2016

This Order is being introduced because of works to install ducting for a hot water steam system, communications and high voltage electricity for a joint hospitals energy link – which is anticipated to take variously until the end of June 2016 to complete. The effect of the Order, when appropriate traffic signs are displayed is to temporarily prohibit parking/waiting and to close to traffic various sections of road and junctions as follows, and the works to progress as shown below:

Closures                                           Dates             Diversion

All Saints Road Between Latimer Road andStapleton RoadLatimer Road from

All Saints Road for approximately 15 metres north-westward

Stapleton Road from

All Saints Road for approximately 15 Metres

Monday 4 to Sunday 17 January To access Stapleton Road:All Saint Road, Lime Walk, Old Road and vice versaTo access Latimer Road:

All Saints Road, Lime Walk, A420 London Road and vice versa

To access All Saints Road (West):

All Saints Road, Lime Walk, Old Road. Bickerton Road and vice versa

Stapleton Road – Entire length progressively in stages north to south between All Saints Road and Old Road Monday 11 January to Tuesday 15 March All Saints Road, Lime Walk, Old Road, Bickerton Road  and vice versa
Latimer Road – Phase 1.Between A420 London Road and Latimer GrangePhase 2. Between Latimer Grange and All Saints Road Monday 21 March to Thursday 30 June A420 London Road, Lime Walk, All Saints Road and vice versa for both Phases
Sandfield Road –North to south in three phases: Phase 1. Between Woodlands Road and Beech Road Monday 1 February to Tuesday 22 April Sandfield Road, A420 London Road, Headley Way, Woodlands Road and vice versa
Phase 2. Between Beech Road and the southeast property line of No.1 Sandfield RoadPhase 3. Between the Southeast property line of No 1 Sandfield Road and the junction withA420 London Road As above when appropriate traffic signs are use A420 London Road, Headley Way, Woodlands Road, Sandfield Road and vice versa.

 

All Resident Permit Parking, Shared Parking, Disabled Parking and other Restricted Time Parking Bays at the following locations on both sides of the road and footway will be suspended when shown by appropriate traffic signs and cones. As the works progress parking bays will be made available.

Parking Prohibitions                                                         Dates

All Saints Road – Between Latimer Road and Stapleton RoadLatimer Road – from All Saints Road for approximately 15 metresStapleton Road – from All Saints Road for approximately 15 Metres

 

Monday 4 to Sunday 17 January 2016
Stapleton Road – Entire length progressively in stages north to south betweenAll Saints Road and Old Road Monday 11 January to Tuesday 15 March 2016
Latimer Road Phase 1.Between A420 London Road and Latimer GrangePhase 2. Between Latimer Grange and

All Saints Road

Monday 21 March to Thursday 30 June 2016
Sandfield Road – Progressively north to southPhase 1. Woodlands Road to Beech Road Monday 1 February to Tuesday 22 April 2016
Phase 2. Between Beech Road and the southeast property line of No.1 Sandfield RoadPhase 3. Between the southeast property line of No.1 Sandfield Road and junction with A420 London Road As above when appropriate traffic signs are use

Exemptions are included for emergency services, the works and essential access.

This Order will remain in force for a maximum period of 18 months or until the works have been completed whichever is the sooner.

The relevant parts of the following Traffic Regulation Orders (as amended) will be temporarily suspended as required for the duration of the works: The Oxfordshire County Council (Headington West) (Controlled Parking Zone) Order 2000;The Oxfordshire County Council (Headington Central) (Controlled Parking Zone and Various Restrictions) Order 2005;The Oxfordshire County Council (Disabled Persons Parking Places – Oxford) Order 2010.

Traffic Regulations Team (Ref. ACP/T3091/T3092/T3093/T3094) for the Director for Environment & Economy, Speedwell House, Oxford OX1 1NE. 0845 310 1111.

There are maps of the road closure areas in .pdf form, please click on the required link to view and please credit Headington Lib Dems if you will use this information in any social media message

001 All Saints Road Part 1 002 All Saints Road Part 2 007 Latimer Road Part 1 008 Latimer Road Part 1 019 Stapleton Road Sandfield Rd Part 1 (2) Sandfield Rd part 2 (2) Sandfield Rd part 3

 

Trust apologises for poor comms with residents over energy project

Last night’s public meeting was well attended with over 100 people turning up.

Residents received an apology for the lateness of the communication.

All residents were given the opportunity to ask questions of the speakers who were from the Hospitals’ Trust and from the contractor, Vital Energi.

There appears to be a further delay in responding to residents because the project team at the Trust has a vacant post to fill, but residents and councillors stressed the need to have much more detailed information as quickly as possible.

The Trust has stated that residents in affected areas will be notified by letter at least two weeks in advance of work starting in their area.

The speakers agreed to hold regular meetings with a residents liaison group and we are setting dates for this today

If anyone wishes to join this residents and contractors liaison group, please let Ruth or Roz know

Your Councillors are working on the following issues:

  • set dates for liaison meetings before Christmas
  • ask the County Council for assistance with temporary relaxation of parking on DYLs or ask if temporary resident parking permits can be issued while works are ongoing in closed off roads
  • enquire who is liable for damage caused to cars parked on street rather than off road in terms of insurance claims, also whether residents need to inform their insurance companies that this change of arrangements is being made and whether this request would incur a charge
  • investigate arrangements for disability access while works are happening outside the property
  • ask the Trust and Vital for a copy of the impact assessment made prior to the works
  • liaising with the Trust’s energy team on financial information supporting the project

Oxford Brookes University has offered to make parking space available for residents overnight at Headington Hill Campus.

120m of trench will be open at any one time. Each section of works will be fenced off, dug, the pipes will be welded together in 12m lengths and laid in the trench with the cable, the trench will be closed and backfilled, then onto the next section

There are plans to keep a disabled parking pick up point available at the end of the trench, and a turning point there is also being considered.

Emergency vehicles will be given access at all times. Refuse collections will continue but earlier than usual, and residents should move their bins to the gate by 7am for collection.

Works will be carried out between 8am and 5.30 pm. Contractor parking is confined to the hospital compounds.

Issues and problems should be reported to the following contacts, preferable accompanied with a photo:

hospitalenergyproject@ouh.nhs.uk

01865 220600

@ouh_estates #energy

copy to Roz, Ruth and Altaf (see contact details above)

.pdf maps of road closures will be posted on this site later today

Public meeting about the hospitals’ energy project

PUBLIC MEETING

Wednesday 9 December

7:00-9:00 pm

All Saints Church House, New High Street, OX3 7AL

​Works are due to start on trench digging in residential roads from 4th January but there has been an embargo on communications until the press launch earlier this week.​

We know our residents are worried because they don’t know what’s going to happen or when, and there will be a number of road closures during which no through traffic will be allowed, although footpaths will still be accessible.

We are pleased to say that reps from both the hospitals’ trust and the contractors have agreed to come along and answer questions from the public, so it should be a very lively meeting

The Trust has published answers to our residents’ list of questions on their website

We are sorry there hasn’t been much notice of this meeting but we want to hold it as soon as possible given the levels of anxiety shown at last week’s Ward Focus meeting

 

Festive singing at Headington Library on Saturday

Barton Sings will share festive songs at Headington Library on Saturday 5 Dec. between 2:00 – 2:30. The group meets weekly in Barton,and will be encouraging people to join in.

Barton Sings is an inclusive, integrated singing group where about a third of participants have dementia or are supporting someone with dementia.

If you are in Headington at the weekend please do join Janet Stansfeld, community singing practitioner, and the group sing in that festive feeling!

https://www.oxfordshire.gov.uk/cms/events/headington-festive-singing

Find out more about Sound Resource – promoting wellbeing through singing and music at http://soundresource.org.uk/

Thanks @Blanchford for donating bags for conservation volunteers!

Residents at a recent Ward Focus Meeting asked if used Blanchford bags could be made available for use by conservation volunteers including the Friends of Lye Valley and allotment associations.

We asked Blanchford’s and they have kindly offered to donate 100 of these big bags, and we thank them for their generosity.

If you belong to a conservation group or voluntary environmental group and would like to put these bags to good use, please contact Ruth, Altaf or Roz

Road closures latest (hospital energy project)

As you know, councillors were very concerned that a number of major roads would be closed at the same time during the energy project works.

County Cllr Roz Smith took up cudgels on our behalf and has received the following welcome news from the County Council:

After discussing at length  there will not be two sets of traffic lights at the same time on Old rd and London rd, however to avoid using three way lights on London rd we will use two way lights when Latimer Road is closed. We have been in contact and had meetings with Vital Energi (contractors for the project) and we are in contact with them on daily basis.

Relief is at hand for late night shoppers in Headington

Inline images 1

Following our request for WC availability after 17:00 in Headington, we’re delighted that the City Council’s Streetscene team has enabled one of the Bury Knowle Park toilets near the London-bound bus stop to open 24/7.

We hope this will help residents and visitors caught short in the evenings, and encourage folk to use our restaurants, cafes and shops into the evening.

Headington is the only district centre with this facility.

Latimer Road application

The application to demolish residential houses at 36, 38, and 40 London Road and 2 Latimer Road and erect 167 student study rooms etc and 4 maisonettes was refused by East Area Planning Committee this evening on grounds associated with planning policies CP1, CP8. CP12 and CS18

We now wait to see if this application will be called in to the Planning Review Committee which would need the support of 12 councillors

The next scheduled meeting of the Planning Review Committee is 23/12/15 at 6.00pm at the Town Hall

The applicant has agreed to include funding for a parking barrier in Latimer Grange subject to agreement with Hastoe.

 

 

 

 

 

 

 

Reaction to hospital energy project briefing

All three Headington councillors attended the briefing today and asked questions about the project.

Fibre optic cables and high voltage cables will be laid within the trench containing the energy pipes.

Roads will be closed at either end while works are being carried out, however footpaths will remain open. The timetable for road closures has been discussed with Oxfordshire County Council and are as follows:

All Saints Road 4/1/16-27/1/16

Stapleton Road 11/1/16-15/3/16

Old Road 23/2/16-13/4/16 (part: controlled by traffic lights)

Sandfield Road 1/2/16-22/4/16

London Road 9/3/16-14/4/16 (part: controlled by traffic lights)

Latimer Road 21/3/16-30/6/16

When complete road closures take place, roads will be closed from either end with no through traffic.

We gave your 20 questions (see earlier post) to the Trust’s Director of Planning and Information and he has undertaken to post the answers up on the website as Frequently Asked Questions

We are trying to arrange a public meeting at All Saints Church House, New High Street on Wednesday 9 December from 7:00-9:00pm and will confirm this shortly. The Trust and Vital Energi (the contractor) have been invited to this meeting which is being arranged with assistance from Highfield Residents’ Association and have expressed interest in attending

We remain concerned that road closures are so long, and that several main routes will be closed at the same time. We are also concerned that Access to Headington roadworks may coincide with the energy project works. At this time we have no information about alternative arrangements for parking for affected residents and there are many questions still unanswered. We note that the Trust has apologised for the lateness of its communications – we believe that much of the anxiety by residents could have been minimised if consultation had happened months ago when the road markings were first apparent.