Energy pipe works set to start on 28 November in Highfield

Conditions attached to the planning consent have now been signed off. Letters are being distributed today by the Oxford University Hospitals Trust outlining the schedule of works. A 12 page booklet will be distributed mid-November giving fuller details e.g. the times of day works will be carried out, how to obtain visitors’ parking permits when the works are immediately outside your property, and other useful information. The proposed dates for works are always provisional at the start of a major project because of external circumstances – a protracted period of bad weather for example. If dates are delayed, residents will be notified of the revised timetable for works but we hope this eventuality will not arise.

From Monday 28 November to Friday 16 December, there will be three-way traffic lights at the Lime Walk/All Saints junction, and the 4th arm of the crossroads will be closed off between the midpoint of the entrance to Barrington Close and the above junction. Lime Walk will remain two way during that period, and access to Barrington Close will be from Bickerton Road and Stapleton Road. The planters at the junction will be removed and stored until the works are completed and will then be returned. Some bollards may be removed and stored temporarily during the works.

From Monday 28 November to Friday 16 December, the top of Latimer Road will be closed as far as the midpoint of the entrance to Latimer Grange.  There will be no entry to Latimer Road from London Road. Those wishing to access Latimer Road from London Road will need to take a different route, either via Gipsy Lane/Old Road/Bickerton or Stapleton Roads; or via Lime Walk and a wait at the three way lights, Old Road, and either Bickerton or Stapleton Roads.

Works affecting Sandfield Road will not start until the New Year.

Contact numbers for information

Daytime: Jo Lennon 07342 086843 (9am – 4.30pm)

Email: hospitalenergyproject@ouh.nhs.uk

Website: www.ouh.nhs.uk/about/developments/energy

Twitter: OUH_Estates #OUHEnergy

More details will be made available in the Trust’s booklet which is currently being printed. Ruth, Roz and Altaf have ensured that the County’s Networks, Access to Headington and Parking Teams have been fully involved throughout. Vital Energi, the contractors for the Trust, are working co-operatively with Winvic, the contractors for the Beech House development, over access to the Beech House site from Latimer Road.

If you require further information, please contact Jo (number above) or your local councillors Roz, Ruth and Altaf

How to contact your councillors

By phone:

Roz: 07584 257156

Altaf: 07931 345554

By email:

Ruth: ruth.wilkinson@oxfordlibdems.org.uk (email preferred)

Twitter:

Ruth

@ruthwilk

 

 

Leave a Reply

Your email address will not be published. Required fields are marked *