2012 scheme:outbound bus lane for London Rd.

We are grateful to County Cllr Roz Smith for sending us the following information from County Traffic Planners:

OCC’s successful bid for money from the Local Sustainable Transport Fund (LSTF) includes £500,000 towards an outbound bus lane on London Road (total cost £1 million).  The length of road in question is from the end of Headington shops to the Gladstone Road bus stop from where there is already a short length of outbound bus lane up to Green Road Roundabout.

The programme for the bus lane is as follows:

  • Oct 11 – Jan 12 Outline design
  • Feb 12 – April 12 Consultation
  • May 12 – Sept 12 Detailed design
  • Oct 12 Scheme approval
  • Jan 13 – April 13  Scheme preparation
  • May 13 – Sept 13 Construction

This is an indicative schedule only at this stage.