Programme of construction work on the London Road

The Site Agent for Oxfordshire Highways has contacted residents living near the London Road to let them know the schedule for roadworks. I thought it would be useful to reproduce this information below.

North side from Pullens Lane to Headley Way 21 July – 20 October 2008

  • diversion of underground services
  • carriageway widening
  • drainage works
  • reconstruction and re-paving of the footways
  • installation of new traffic signs

North side from Headley Way to Osler Road 21 July – 13 October 2008

  • diversion of underground services

North side from Headley Way to Osler Road 18 August – 17 November 2008

  • carriageway widening
  • drainage works
  • resonstruction and re-paving of the footways
  • installation of new traffic signs
  • preparation work for changes to traffic signals

South side from Brookside to opposite Pullens Lane 20 October – 11 December 2008

  • diversion of underground services
  • carriageway widening
  • drainage works
  • reconstruction and re-paving of the footways
  • installation of new traffic signs
  • preparation work for changes to traffic signals

South side from New High Street to Brookside 17 November – 19 Jan 2009

  • diversion of underground services
  • carriageway widening
  • drainage works
  • reconstruction and re-paving of the footways
  • installation of new traffic signs
  • preparation work for changes to traffic signals

Oxford Brookes University public space area 18 December – 13 January 2009

  • installation of new kerbing
  • drainage works
  • installation of high quality paving materials on the footways
  • re-positioning and upgrading of the Pelican crossing outside the Gipsy Lane Campus
  • installation of new traffic signs

Headley Way to Osler Road 19 January – 9 February 2009

  • installation of traffic lights and pedestrian islands
  • re-surfacing of the road
  • installation of new road markings

Pullens Lane to Headley Way 26 January – 23 February 2009

  • installation of traffic lights and pedestrian islands
  • re-surfacing of the road
  • installation of new road markings

Regular scheme updates will be posted on the County Council’s website

The Oxfordshire Highways Enquiry Line is 0845 310 1111