Here is the January newsletter from the Beech House site in Latimer Road.

Progress on site:

Concrete works to the basement is almost complete, unfortunately we have suffered a few delays in January due to the drop in temperature again. We have erected a protected walkway over the footpath, this will be in place for the duration of our main deliveries into site. The steel frame has been started today and should now progress quite quickly.

Work to be progressed over the next 4 weeks:

We shall be completing the concrete works to the basement and starting the foundations to the maisonette’s mid February. The steel frame will progress along with forming the floor slabs. We are also starting to erect the scaffold around the steel frame.