In response to complaints by residents in the area, Altaf and Ruth have agreed match funding with Oxford City Highways Engineering to fix potholes, patch road edges and surface skim (where necessary) Woodlands Road either side of Headley Way up to the Sandfield Road junction with money from Headington Ward’s CIL budget and Vital Energy community contribution.
Half the work is likely to be completed by the end of this financial year (end of March) and the rest is scheduled for the start of the new financial year. It is likely to take 5 or 6 days in total, exact dates to be confirmed.
Ruth comments:
We have wanted to get this work done for some time, but have needed to save up for it as the total cost is over £2300. We are grateful to Oxford City Council and Vital Energi for their assistance with funding.