Beech House monthly update

Simon Houldsworth is the new project manager for the Beech House works in Latimer Road.

 

He reports as follows:

Progress on site:

Concrete works to the basement is progressing well, despite the drop in temperature and the limited access to site. We have managed to make our drainage connections in Latimer Road during the Vital energi works to reduce the impact on the access to Latimer road at a later date.

Work to be progressed over the next 4 weeks

We shall be completing the concrete works to the basement and starting the foundation to the maisonettes, as well as setting up a material delivery area.

Christmas shutdown

We will shut down for Christmas on Friday 23rd December and return on Wednesday 4th January.   There will be full time security on site all over Christmas.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 