Here are unconfirmed notes taken from yesterday’s meeting of the developers/construction company with the community. We are finding it progressively more difficult to help co-ordinate building works in what appears to be an absence of any work schedule for the Access to Headington project. We are bombarding the County Council’s A2H team with requests for information on what will happen when!
Issues so far
- Latimer Grange residents very upset by noise from piling work RW. Piling work will stop on Friday, machinery will be removed Mon/Tues next week
- Start times adjusted following complaint from RW
- Complaint from RW re car in Latimer Grange private space into which a worker on site had driven into at speed and parked displaying a notice “car broken, waiting AA” had been resolved by site manager
- County Networks had complained the road needed wetting and cleaning, this has been done
- Winvic staff very helpful in helping elderly residents cross the road (McMaster House and RW)
Current situation
- Had met Planners this morning, useful meeting. Need to look at resolving some issues incl. ramp from London Road entrance – concerns about tree roots, bin storage areas, waiting for reply from Headington School re fins/window treatments
- Promised to reinstate pavement for McMaster House – have already tarmacked the other side and McMaster House warmly appreciative
- Promised to sort out the half-block wall outside which now looks unattractive
Outstanding issues
- Contribution towards Latimer Grange barrier ready to be made but don’t know who is going to do the work. (RW chase Hastoe Housing Association manager)
- Newsletters have ceased after the one in May, site manager will issue a brief sheet explaining what has been done so far and what will happen over the next 4 weeks
Likely timetable
- For the following 6-8 weeks, Cairncross will deal with ‘civil works’ within the curtilage
- Storm water drain connection will necessitate works in London Road. Likely to be Jan/Feb but plans still to be drawn up
- Co-working in close proximity with other major projects needs to be more joined up (RW chase County again for Access to Headington plan and speak to County Networks about tie-ing in works with Vital Energi if the pipe application gets consent)
- Drainage/sewerage issues – existing pipework may be insufficient diameter, certainly in Latimer Road and Brookside (RW asking Drainage team for advice before contacting Thames Water)
- Tower crane needed end Oct/early Nov. Jib needs to be assembled in 36m of space before attaching to mast. There may not be enough room on site to do this so likely to ask Networks for road and footway closure at top of Latimer Road on a Saturday (date to be confirmed, could be beg. November)
Contacts on site
- Site Manager is going on holiday 17/8
- Mick Walsh taking over rest of this week, we have his contact number
- He goes on holiday for Bank Holiday week so there will be a relief manager sent there for the 3 working days of that week, details not yet known. Mick will inform stakeholders
All questions to Ruth (RW) please.