We have left an A3 hard copy version of the Construction Traffic Management Plan relating to the energy pipe application at Headington Library for residents to study. This is a work in progress and subject to change.
The planning committee meeting about the energy pipe application is going to take place on 7th September. The construction traffic management plan is being prepared now by the County Networks Team and the applicant and will only come into operation if planning consent is granted.
We are working closely with the County Networks Team which manages traffic when works happen. They have asked us some questions which we shall be talking to residents about:
- Lime Walk South is likely to be one way only (downhill direction towards London Road) while works are ongoing in that area. Do residents consider that Bickerton Road and Stapleton Road could usefully be made one way while works are happening between London Road and Old Road?
- Should access to the above area be signed “Access to frontages only” while works are on-going?
- The works to All Saints junction would make it trickier for residents in New Headington to access their properties – do they think that the bollards at the end of Bateman Street should be removed temporarily so that people who live in Piper, Windsor, Wilberforce, Perrin, Bateman Streets and Kennett Road will have a second route in/out during the period these works are happening? (c3 weeks)
Please let us have your views on these issues as there is limited time to influence this traffic management plan to best advantage.
At present it seems that the County meeting held in public on whether consent should be granted for a street works licence will happen at 2pm on 5/9 with a City briefing on the legal implications to councillors in public very very soon afterwards (date to be confirmed) and certainly before 7/9.