First newsletter about Beech House development (Latimer Road student accommodation)

We have received the first newsletter from Winvic and reproduce it in full for our residents’ information.

PROJECT INTRODUCTION

MAY 2016

Project title – Beech House, Latimer Road, Oxford, OX3 7PF Project duration – 59 Weeks

Current Week No. -1

INTRODUCTION/PROJECT DESCRIPTION

Winvic have been appointed to construct the Beech House student accommodation development on Latimer Road, Oxford.

The project comprises of the demolition works to 4 existing dwellings inclusive of external walls and garden sheds.

A temporary heras fence will be installed to the perimeter of site to allow the external walls to be demolished to allow the permanent timber hoarding to be installed.

The main development consists of the construction of a five storey Student Accommodation ground with basement & a 4 storey Residential Accommodation in a separate apartment block, adjacent to main development.

The main elements of the development will consist of secant piling and tanking works to the basement, steel frame, brick work, render, external windows and roof works.

Works and phasing will take into account the neighbourhood and congestion.

SITE TEAM

HOW TO CONTACT US…

We will keep you regularly updated on the status of the works with a monthly newsletter, however should you have any queries or concerns regarding the project please do not hesitate to contact our Project Manager, Nick Lakin 077209 71948.

OTHER INFO…

The associated Demolition works for the Project are due to commence on site during week commencing 31st May 2016.

However, the initial works which comprise of the erection of temporary Fencing to allow the boundary walls to be removed and the installation of the permanent timber hoarding are due to commence during week commencing 23rd May 2016.

Throughout our works we will liaise closely with the surrounding Businesses and Residents and issue regular newsletters highlighting our forthcoming works.

  • Vehicular traffic will be monitored and major deliveries booked in to minimise any disruption caused to local businesses and close neighbours.
  • Site logistic plans will be posted at the front of site and updated within the newsletters.
  • Dust and noise will be monitored throughout our works working closely with the local authorities to manage our construction works as efficiently as possible.

Nick Lakin

Project Manager
Winvic Construction Ltd
Brampton House, 19 Tenter Road Moulton Park, Northampton NN3 6PZ

T +44 (0)1604 678960 F +44 (0)1604 671021 E mail@winvic.co.uk

  • At Winvic we believe in working closely with community to minimise any disturbance our works may cause and will be enrolling in the considerate constructor’s scheme to ensure only the highest standards are achieved.

CONSIDERATE CONSTRUCTORS SCHEME

As another element of our quality control, we aim to reduce the impact of our work on the neighbours by following the codes of practice set out in the Considerate Constructors Scheme [CCS], to which all Winvic projects are entered. This automatically measures how we deal with public questions and complaints.

BEECH HOUSE, LATIMER ROAD, OXFORD, OX3 7PF

Leave a Reply

Your email address will not be published. Required fields are marked *