Ruth met a number of local residents and University employees at last Friday’s public consultation meeting. Here is the proposed timescale for development that was advertised at that event:
9-10 May 2014
Public consultation on detailed design of BDI building, and initial proposals for Amenities building
End of May 2014
Submit reserved matters application for BDI building
June 2014
Public consultation on Amenities building
June-September 2014
Council consideration of BDI building application and consultation period for comments from the public
July 2014
Submit reserved matters application for Amenities building application
July-October 2014
Council consideration of Amenities building application and consultation period for comments from the public
October 2014
BDI building: start on site
January 2015
Amenities building: start on site