Update from Oxford Brookes on the building work

Local councillors have received this report from Oxford Brookes University

1. Works Update

1.1. Scaffolding around the site is expected to be removed from the beginning of July

page1image5024

1.2. Trench digging work has progressed significantly at the face of our Media Centre building (next to Headington Road)

1.2.1. This will continue into the summer and requires breaking and excavation that may cause noise, vibration and dust disturbance to those residents close to the area

 

1.3. The programme of concrete breaking and excavation along the Western Access Road will continue into July outside the Tonge building and International Centre

1.3.1.  Paving work to complete the look of our new campus will soon begin along the face of Tonge

1.3.2.  From early July, excavation work will progress to the face of the International Centre and continue on to the Media Centre and is expected to complete in September

1.3.3.  The process of breaking, excavation, ground preparations and paving required by this work may cause noise, vibration and dust disturbance to nearby residents

1.4.  Alterations to access along our Western Access Road as described in previous Reports are now in effect – please see point 3 below

1.5.  Traffic on Headington Road will benefit from a drop in the number of HGV deliveries arriving on to site via the Western Access Road as work to the piazza and building entrance progresses in July

 

2. Removal of Tower Crane 2

2.1.  Tower Crane 2 will be dismantled and removed from the site between Saturday 29 and Sunday 30 June, over weekend hours

2.2.  The removal will involve the erecting of a temporary support crane close to our Western boundary and the Tonge building

2.3.  On Saturday 29 June work will begin at 7am and continue until 7pm

2.4.  On Sunday 30 June work will begin at 8am and continue until 6pm

 

3. Changes to Western Access Road

3.1.  A temporary fully accessible path has been established at the rear of our International Centre and Tonge buildings

3.2.  Work to extend this path via the rear of the Media Centre has been rescheduled in line with programmed breaking and excavation works adjacent to this building

3.3.  This extension is now expected to be constructed later in the summer, after which we will close the entire Western Access Road to public traffic while final paving work is completed

3.4. The extended temporary path will then remain in operation until the completion of the project

 

 