Details of road works starting 9 January Old Road/Lime Walk

Phase 2 of the New Headington Transport Improvements Scheme will be starting on 09 January 2012.  The County Council will be carrying out traffic calming works at the side road junctions on Old Road in Headington and 2 junctions on London Road.  They will write to residents of each road where  they will be carrying out the works to inform them of the road works and the traffic management arrangements they have organised.
 
Road works are programmed as follows:
09 January to 17 January 2012 – junction entry treatments on Old Road (Valentia Rd, Finch Close and Highfield Avenue)
18 January to 27 January 2012 – junction entry treatments on Old Road (Bickerton Rd, Stapleton Rd) + new Zebra crossing on Old Road
30 January to 07 February 2012 – junction entry treatments Old Road/Lime Walk junction + London Road/Latimer Road junction
08 February to 17 February 2012 – junction entry treatment at London Road/Lime Walk junction
 
Works on Old Road will be carried out during ‘off-peak’ hours of 09.30 to 15.30.  Works will be carried out under temporary traffic signal control on Old Road in order to divert pedestrians out of the working area.  Pedestrian access will be maintained to the side roads however.  Side roads will be closed to through traffic for the duration of the works unless they are cul-de-sacs.
 
Works on London Road will involve diverting pedestrians away from the working area and into London Road.  Pedestrian access will be maintained.  They are not anticipating having to use off-peak traffic lights for works on the side road junction off London Road.  Side roads will be closed to through traffic for the duration of the works.
 
A local diversion route will be in operation during each of the road closures.

Please email us if you would like a map

Leave a Reply