Latest on Access to Headington

We have just received this information from the County Council.

You will all no doubt be aware the Oxfordshire Growth Board announced the Year 1 growth project allocations yesterday and A2H received the full monies asked for. The announcement came a week earlier than we were expecting, it means that the Headley Way works will be continuing as originally scoped. 

I will update you with more information when I have it but the intention will be to start the Headley Way works after Easter, an Easter start would then have the programme running to Christmas 2018 (weather permitting). We will start at the Marsh Lane roundabouts as per our original programme but the programme at the JR access will be changed as we’ve managed to do some early works in advance that should reduce the disruption there.

As before, we will be undertaking a pre-construction exhibition at a location/time TBC.

The funding announcement also allows us to reintroduce elements of the work that were removed from scope including the pedestrian crossing on London Road at the Osler Road bus gate. A plan is attached showing the proposals for your information.  The proposals differ from the originals in the following way:

  • Original provision showed a toucan crossing incorporating the bus gate, after developing the design further it was determined that a controlled crossing could not be delivered safely.
  • Alternatives were considered, including a zebra, which had similar safety concerns.
  • The best alternative was to provide an uncontrolled crossing, incorporating a build out to shorten the crossing and providing a refuge in the middle of the road
  • There remains a broad local support for pedestrian provision in this location but bus companies are understandably concerned that the changes may affect the level of bus priority they receive with this latest proposal and we’re engaging with them to mitigate their concerns.

We will be looking to start the work as soon as possible, taking advantage of the Easter holidays if at all possible. It’s envisaged that the work would take 6-8 weeks given the site constraints.  We will be publicly advertising the attached shortly and will advise of the programme of works and TM phasing once approved by network management.

We are checking that works to trees can be done at this time, bearing in mind that this is the start of the nesting season.

One thought on “Latest on Access to Headington

  1. One more clarification – The total £3.5m funding for A2H is split over 2 financial years. £3m in Year 1 with an additional £0.5m in year 2.

Leave a Reply to Ruth Wilkinson Cancel reply

Your email address will not be published. Required fields are marked *