The start of the next phase of the Access to Headington transport improvement project has been postponed.

Work had been due to start on Headley Way on 22 January along the length of Headley Way including the junction works outside the John Radcliffe hospital and on the Marsh Lane junction.

However concerns over costs, utility diversions and technical issues relating to the hill section between Marsh Lane and the hospital, mean that the construction team have decided to put the start on hold. This means that the team are now looking at other sources of funding along with ways to reduce costs so that the improvement work goes ahead.

However the need for more certainty over costs, utility diversions and technical issues relating to the hill section between Marsh Lane and the hospital, mean that the construction team have decided to put the start on hold. This has also provided an opportunity to seek additional sources of funding to include improvements that had previously been unaffordable along with ways to reduce costs so that the improvement work goes ahead.

It is hoped that a new date for the work to start can be decided in the coming weeks.

County Councillor Yvonne Constance, Cabinet member for Environment and Economy, said: “We are still committed to delivering the scheme and some facilitating work will continue at weekends so that we are ready

“This is a challenging and much needed piece of work and it makes sense to look again at the costs and designs to ensure that it can be delivered on budget. We had hoped to resolve this without needing to pause the scheme but require more time to reach a conclusion.”

Work on The Slade is programmed to finish in February providing a new off-carriageway facility for cyclists as well as improved crossings. Once complete known issues such as parking obstructing the path will see enforcement action taking place.

The new junction on Gypsy Lane, completed early 2017, is working well and we will continue monitoring of that over the duration of the Access to Headington programme. The latest work undertaken on Old Road/Churchill Drive and Churchill Drive/Roosevelt Drive is now complete and working well providing improved access for the Churchill Hospital site.

One thought on “Press release re A2H delay

  1. Mike Ratcliffe says:

    Intrigued by the two slightly different paragraphs that start ‘however’ as if the press team had two versions and left both in.

    For those of us concerned about the point of much of the A2H work, this is a vindication. However, looks like the County will press on regardless of evidence…