Energy pipe update

Here are the official notes from last week’s liaison meeting between Trust, Vital Energi, councillors and resident representatives.

Project manager ENERGY LINK UPDATE:

Lime Walk:

  • Going well and now around 6m from the Old Road junction.
  • Traffic ignoring the All Saints Road No Entry/One Way signs still a problem.
  • Could VE/Trust discuss the TMP for the work on Old Road/junction of Lime Walk as resident rep has serious concerns about everyone’s safety. VE/Councillors have a meeting on Tuesday 28 February with Highways and confirmed that this will be discussed.
  • Historic damage (by ‘moled’ gas work) to the main drain has been fixed by VE.
  • VE has also cleared silted drains where possible.
  • Thames Water will be in Lime Walk later this year to fix a leaking hydrant at the All Saints Road junction. This an historic problem and is nothing to do with VE.

 

Old Road:

  • A2H roadwork at Gipsy Lane has finished and, as their temporary lights have been lifted, VE will start Trial Holes on Old Road from Monday 27 February. The Trial Holes are being done to locate underground services and, therefore, establish the best route for the Energy Link.
  • There will be three-way lights (East/West on Old Road and Northbound out of Churchill Drive) for the trial hole work.
  • The work to cross Old Road will start on 8 March. At which point Churchill Drive will be closed and there will be two way (East/Westbound) lights on Old Road.
  • Traffic lights will be manned during peak hours (6am – 9am and 3pm – 6pm)
  • Work is 7 days a week and 7.30am – 7pm Monday – Friday; 8am – 4pm on Saturday and 9am – 2pm on Sunday. (TBC).
  • Work will start in the centre of the road and work back to Lime Walk with traffic passing on the hospital (westbound) lane. When this is complete, the work switches to the other carriageway and traffic is on the Lime Walk side of the road (eastbound carriageway) and from there, down Churchill Drive.
  • The welfare unit will be located by the Energy Centre off Churchill Drive.

 

Latimer Road:

  • Currently, three days delayed because of unknown services and a large concrete culvert. In addition, the gas supply lines to three houses is shallower than others in the road and so the gas pipes are touching the Energy Link. Southern Gas Network will take 28 days to come and do ‘Multiple Alterations’ (a loop on each house’s supply pipe). VE will therefore continue with the current work programme but leave these three areas enclosed in by 3.5m fencing so that they can be tarmacked after the gas board has done the remedial work.
  • The current work section is slightly longer than originally planned because, following discussion with residents, VE has extended the current trench in order to reduce the disruption to residents who live at the end of Latimer Road near the All Saints junction.
  • The reinstatement on Latimer Road and does not follow a dead-straight route as VE has also been fixing poor tarmac and blocked drains (this has been done in close conjunction with the City and County Highways teams).
  • VE was able to work outside 21-25 without causing any further disturbance to the badly degraded pavement, so this will not now be replaced.

 

Sandfield Road:

  • Three days late because of “moled” unmarked services, but might be able to make some of this time up in the next section (Beech Road – Woodlands Road).
  • Roz mentioned that a resident had been unhappy about the start date being delayed and signage, but generally positive comments about the work.
  • Project manager confirmed that the signage for the Manor Hospital/Beech Road has been put out on Headley Way and Woodlands Road. The Manor Hospital had confirmed that the new wording was a significant improvement.

 

London Road:

  • VE will be a week late onto London Road because they cannot start this section UNTIL the work on All Saints Road is complete (otherwise Latimer Road would sealed at both ends).
  • There will be manned two-way lights on London Road with no entry/exit to London Road from Latimer Road OR Sandfield Road. This is to avoid a four-way set of traffic lights.
  • The Bus Lane will be suspended between Pickwicks Guest House and the Red Mullions and all traffic (including buses) will be corralled into one lane for this stretch.
  • Work is currently planned: 3-28 April, 7 days a week and 7.30am – 7pm Monday – Friday; 8am – 4pm on Saturday and 9am-2pm on Sunday. (TBC). Work will carry on through the Easter weekend.
  • The welfare unit will be located in Sandfield Road in the 4-hour parking bays.

 

OTHER:

It was agreed that there was no need for further residents’ meeting as the work on residential roads is largely complete. Jo will email updates and any substantial changes.

Jo Lennon thanked Councillors and residents for their support at these meetings and in general over the last 14 months and closed the meeting.

Leave a Reply

Your email address will not be published. Required fields are marked *